How to plan an office fitout: a guide for Melbourne businesses

The short answer. Start with how your team works, not how the office should look. Set a budget range, then work back from your lease end date: around 12 months out if you're moving, and at least 4 to 6 months if you're staying. Have a builder look at any space before you sign, and make the big decisions on paper, before construction starts.
Most people planning an office fitout have never done one before, and there’s no reason they would have. It comes around every five or ten years, usually while you’re also running a business. In more than 10 years of office fitouts, and more than 100 projects, I’ve found the ones that go best get a handful of things right early.
This is the order I’d plan an office fitout in, with rough costs and timings. Most sections finish with one small thing you can do this week.
How do you plan an office fitout?
Plan it in this order: understand how your team works, set a budget range, check the lease and the building, bring in a fitout team, settle the design, then build. Working in that order means the expensive decisions get made on paper, where changing your mind costs very little.
The step people most want to skip is the first one. It’s tempting to start with finishes and furniture, because that’s the enjoyable part. Layout, finishes and furniture all get easier once you know who needs to sit near whom, how many people are in on a typical day and what the space has to do for the business.
Start with your people, not the floor plan
Before anyone draws a line, write down how your team really works. Which teams talk all day, and which need quiet? How many people are in on a Tuesday compared with a Friday? What do people complain about in the office you have now?
Ask the team as well as the leadership group, because the people at the desks notice things that never come up in a management meeting. A good look at your current space helps too. You might find the big communal kitchen gets used for everything from lunch to the monthly all-hands, and that’s worth keeping. You might also find there’s nowhere private to take a call.
Then think 3 to 5 years ahead. A space planned for today’s headcount will feel tight in two years if you’re growing, and how many people come in on your busiest days shapes how much space you need. Our Area Estimator gives you a rough figure in a few minutes.
Try this: ask your team two questions. What’s the one thing you’d keep about this office, and the one thing you’d change?
What should be in an office fitout brief?
A good fitout brief fits on one or two pages. It covers how many people the space needs to hold now and later, the kinds of space your team needs, your must-haves and nice-to-haves, a budget range and the date you need to be in.
Splitting must-haves from nice-to-haves is one of the best ways to keep a budget under control, and we work through it with every client in the discovery stage. A must-have might be acoustic treatment in every meeting room so conversations stay private. A nice-to-have might be an electric sit-stand desk at every workstation. A good middle ground could be sit-stand desks for part of the team and standard desks for the rest.
Add a line about how you want people to feel when they walk in. “Calm, and easy to find your way around” tells a designer more than a mood board does. Some of the brief will be a guess, and that’s fine. It gets sharper once a designer has been through it with you.
Try this: make the two lists, must-haves and nice-to-haves, with your leadership team before your first meeting with a fitout company.
How much should you budget for an office fitout in Melbourne?
For a Melbourne office, a full fitout typically costs $1,200 to $2,800 or more per square metre, including furniture, electrical and plumbing. A refurbishment of an existing office generally comes in at $400 to $800 per square metre. Work with a range rather than a single figure.
Mid-range work usually sits between $1,200 and $1,800 per square metre, and a premium or highly customised fitout starts at around $1,800. Our office fitout cost guide explains what moves the number. If you’re not sure you need a full fitout at all, our post on fitout or refurbishment helps you work it out.
A few costs sit outside the price because they belong to your business: removalists, getting your computers and network working (usually your own IT provider does this) and connecting your own energy and internet. If your lease has a make-good clause, which is the work to return the space to its original condition when you leave, that’s another cost to understand before you commit.
The best results come from being targeted. Put the money where people notice it every day, like the entry, the kitchen and the meeting rooms, and keep the secondary spaces simple and practical.
Try this: list the three places your clients and your team spend the most time. That’s usually where the money should go.
Before you sign a lease, have a builder look at the space
Leasing agents are great at finding space that matches your brief, and it’s also worth having someone who builds fitouts walk through it before you commit. Early space planning shows how your team will actually fit, and a builder can tell you what the space will really cost to fit out, not just what it costs to rent.
Every building is different. The air conditioning, the switchboard, the ceiling and where the services run all affect the price of a fitout, and none of them show up in a listing. Most leases also need the landlord’s consent before you do any work, and many buildings have their own rules on access, working hours and lift use, so it helps to know those early.
Read the make-good clause while you’re at it. It’s much easier to understand at the start of a lease than at the end of one.
Try this: before your next inspection, send us the floor plan and the listing. We’ll tell you what to look at while you’re there, or come along with you.
How early should you start planning an office fitout?
If you’re moving, start around 12 months before your lease ends. If you’re staying and refurbishing the space you have, allow at least 4 to 6 months. The build itself generally takes 8 to 14 weeks, but design, approvals and ordering all come before it. If you’re not yet sure whether to move at all, our post on whether to stay, move or refurbish helps you decide.
A lot of conversations start with “our lease is up in three months”, and three months is rarely enough. When time runs short, decisions you’ll live with for years get made in a hurry. Moving also takes longer than most people expect once you count finding a space, agreeing the lease, design, approvals and the build. Our post on how long an office fitout takes goes through each stage.
Some things add time that people don’t always count. Custom joinery, glass and some furniture can take weeks to arrive. Most office fitouts also need a building permit from a registered building surveyor, and the Building and Plumbing Commission explains when a permit is required in Victoria. We look after permits as part of the project, but they still need room in the plan.
The other thing that slows a project down is waiting on decisions. When an answer takes two weeks to come back, everything behind it waits too.
Try this: find your lease end date and count back 12 months. If that date has already passed, it’s worth a conversation sooner rather than later.
Bring one team in early
You’ll need a designer, a builder, someone to manage the project and keep everything in the right order, and your own IT provider. We put design, approvals and construction under one contract, so you deal with the same people from the first site visit to the day you move in. You don’t have to keep three companies talking to each other. If you do use separate companies, someone has to coordinate them, and that’s a big job on top of running a business. If you’re choosing between companies, our post on what to look for in an office fitout company lists what to check.
Bring the team in before the design is fixed. Moving a wall on paper costs nothing, while moving it once it’s built costs time and money. You can see how we run a project, stage by stage, on our What we do page.
It also helps to have one person inside your business who owns the project and can make a call without taking it to a committee. They don’t need fitout experience, just the authority to say yes or no.
Get the scope in writing and compare like with like
Price differences between proposals usually come down to what’s included, so the detail matters. One proposal might allow for two data cables to each of 100 workstations, and another for one. The second looks cheaper on paper, but if your office needs two, it can end up costing you more.
Ask each company for a written list of what isn’t included, and check the same items in every proposal: power and data, AV in the meeting rooms, joinery, changes to the air conditioning and fire services, permits, furniture, make-good and signage. Ask how changes are agreed and priced, too. Changes are normal on a fitout, and what matters is that the price and any effect on the timeline are agreed in writing before the work happens.
How do you keep the business running during the build?
For a full fitout, your team will need to work somewhere else while the build happens, so plan the move and any temporary space early. A refurbishment is different. Depending on the work, it can sometimes be staged area by area, with the noisy work scheduled around your team.
Either way, it’s easier when the builder knows your busy periods early, like the end of the financial year or a big client launch. Tell your team what’s happening and keep telling them. People cope with disruption far better when they know when it ends.
Where to start
If you only do three things, talk to your team before anyone draws a plan, work back from your lease end date, and have a builder look at any space before you sign. Most of what goes well on a fitout comes from decisions made early, when changing your mind is cheap.
If you’re not sure which step you’re at, Plan your space asks a few quick questions and points you to the guide or tool that fits.
If you’d like to talk any of it through, feel free to reach out. We’re happy to walk through a space with you, look over a proposal you’ve received, or give you a straight read on your budget and timeline, with no commitment.
Frequently asked questions
How do you plan an office fitout?
Start with how your team works, then set a budget range, check the lease and the building, bring in a fitout team and settle the design before construction starts. Work back from your lease end date so the big decisions aren't made in a hurry.
How early should I start planning an office fitout?
If you're moving, start around 12 months before your lease ends. If you're staying and refurbishing, allow at least 4 to 6 months.
What should be in an office fitout brief?
How many people the space needs to hold now and in 3 to 5 years, the kinds of space your team needs, your must-haves and nice-to-haves, a budget range and the date you need to be in.
Do I need a building permit for an office fitout?
Most office fitouts in Victoria need a building permit, issued by a registered building surveyor. Some minor work is exempt. We look after permits as part of the project, but they need time in the plan, which is one more reason to start early.
Do I need a project manager for an office fitout?
Someone needs to coordinate design, approvals, trades and deliveries. If one company designs and builds your fitout under one contract, project management is included.