How much does an office refurbishment cost in Melbourne?

The short answer. A targeted office refurbishment in Melbourne generally comes in at $400 to $800 per square metre, against $1,200 to $2,800 or more for a full fitout. Where yours lands depends on how much of the space you update and how much of what's there can stay. Most refurbishments take 4 to 8 weeks, depending on size.
A refurbishment is often the right answer when the office mostly works but parts of it are holding the team back. The kitchen hasn’t been touched in years, there’s nowhere quiet to take a call, or reception no longer looks like the business you are now.
The question that follows is always the same: what will it cost? Here are the ranges we work with, what moves a project up or down within them, and what to plan for besides the build.
How much does an office refurbishment cost in Melbourne?
A targeted office refurbishment in Melbourne generally comes in at $400 to $800 per square metre. A full fitout typically costs $1,200 to $2,800 or more. Where a refurbishment lands depends on how much of the space you update, how much can stay as it is, and the finishes you choose.
On a 300 square metre office, $400 to $800 per square metre works out to roughly $120,000 to $240,000 if the refurbishment covered the whole floor. Most don’t. A refurbishment usually touches some areas and leaves others alone, so the real figure depends on scope. Our office fitout cost guide sets out the full fitout ranges if you want to compare.
What a refurbishment usually covers
The areas we’re asked to look at most often are kitchens and breakout spaces, reception and entry, meeting rooms (including AV and acoustic treatment), and flooring, lighting and paint across the floor. Phone booths and acoustic booths have become one of the most common requests too, because they give people somewhere to focus without building new rooms.
You don’t have to do everything at once. Any one of these areas can change how the whole office feels, which is why a refurbishment is often planned around the two or three places that matter most. Our post on fitout or refurbishment explains when a refurbishment is enough and when it isn’t.
What moves the price within the range
How much of the floor you touch. This is the biggest factor. A new kitchen and fresh carpet is a very different project from a kitchen, reception, meeting rooms and lighting together.
How much can stay. Ceilings, air conditioning, power and data that still work can usually stay where they are, and every one that stays keeps the cost down. Older services that need upgrading push it up, and some of that only shows once a ceiling is opened. That’s why we get up into the ceiling to see what’s there before the scope is final.
Whether walls move. Moving or adding a wall brings more than the wall itself. A new meeting room often needs sprinklers moved or added, and its own air conditioning control so it doesn’t end up too hot. A refurbishment that keeps the layout and changes the finishes sits toward the lower end.
The finishes you choose. Stone benchtops, custom joinery and feature lighting cost more than practical, hard-wearing alternatives. It usually makes sense to spend on the places people see every day and keep the rest simple.
How the work is staged. If your team stays in while the work happens, it’s done area by area. That keeps the business running, but it can add a little time and cost, because the work moves around the floor more than once.
Try this: walk through the office with two or three people from your team and agree the three areas that would make the biggest difference. That short list is the best starting point for a refurbishment budget.
What it looks like in practice
These are examples, not real projects or quotes, to show how scope moves a budget.
A refresh of paint, carpet and lighting across a floor whose layout still works sits toward the lower end of the range, because nothing structural changes. A targeted refurbishment of the kitchen and breakout, two meeting rooms with acoustic treatment and new AV, and a few phone booths sits in the middle, with the money concentrated where the team spends its day. A refurbishment that also moves walls, adds rooms and reworks services across most of the floor sits at the top of the range, and at some point it becomes a fitout in all but name.
What sits outside the price
A few costs belong to your business rather than the refurbishment: removalists if anything needs to move, getting your computers and network working (usually your own IT provider does this) and any changes to your own energy or internet connections.
It’s also sensible to keep some contingency aside for changes and surprises in the building. How much is up to you and depends on the age of the building.
When you’re comparing quotes, check what each one includes. Two honest quotes can look very different because one covers design, project management and furniture and the other doesn’t.
How long does an office refurbishment take?
A targeted refurbishment generally takes 4 to 8 weeks, depending on the size of the space. A full fitout build usually takes 8 to 14 weeks. Design, approvals and ordering come before the work starts, so allow time for those as well.
Depending on what’s involved, a refurbishment may need a building permit, and joinery, glass and some furniture can take weeks to arrive. We look after permits as part of the project, but they still need room in the plan.
Can you stay in the office during a refurbishment?
Sometimes. Depending on the work, a refurbishment can be staged area by area, so your team keeps using part of the office while another part is worked on. Noisy work may need to be scheduled around your team. Our post on whether you can stay in your office during a fitout covers how to plan for it.
When a refurbishment isn’t enough
A refurbishment works when the layout and the building still suit you. If the layout itself is the problem, the services are past their use-by date, or you’ve outgrown the space, a refurbishment can end up spending money on areas a full fitout would later rebuild.
If you’re not sure whether to refurbish where you are or move somewhere new, our post on whether to stay, move or refurbish helps you work it out.
How to get a number for your own office
The quickest way to a real figure is to have someone walk through the space with you. Plan your space can book a free Space Assessment of your current office, where we look at what needs changing, what can stay and how the work could be staged around your team.
If you’d rather talk it through first, feel free to reach out. We’re happy to give you a realistic read on what your budget will get you.
Frequently asked questions
How much does an office refurbishment cost per square metre in Melbourne?
A targeted office refurbishment generally comes in at $400 to $800 per square metre. Where yours lands depends on how much of the space you update, how much can stay as it is and the finishes you choose.
What is included in the price of a refurbishment?
The refurbishment work itself. Removalists, getting your computers and network working, and changes to your own energy or internet connections are usually arranged by your business. When comparing quotes, check what each one includes, such as design, project management and furniture.
How long does an office refurbishment take?
A targeted refurbishment generally takes 4 to 8 weeks, depending on the size of the space. Design, approvals and ordering come before that.
Is a refurbishment cheaper than a fitout?
Per square metre, yes: $400 to $800 for a refurbishment against $1,200 to $2,800 or more for a full fitout. A refurbishment only saves money when the layout and building still suit you, though. If they don't, a fitout is usually the better investment.