How much does an office fitout cost in Melbourne? (2026 guide)

The short answer. Melbourne office fitouts typically cost about $1,200 to $2,800 or more per square metre, from a mid-range fitout at the lower end to a premium, customised one at the top. That figure covers everything you need to move in and start working from day one, including furniture, electrical and plumbing.
It’s the first question almost everyone asks me, and it’s the hardest one to answer well. The range is wide, and a number given without understanding your space is a guess.
“It depends” doesn’t help much when you’re trying to set a budget, though. So here are the ranges we work with after more than 100 projects, what sits behind them, and where I’d put the money if it were my office.
The ranges, and what they actually mean
Melbourne office fitouts generally fall into two broad categories. A mid-range fitout, with quality finishes, good staff amenities and space that supports a range of uses, sits between $1,200 and $1,800 per square metre. A premium or highly customised fitout starts at $1,800 and can go well beyond $2,800 per square metre. A refurbishment, where you update the areas that need it and keep the rest, generally comes in at $400 to $800 per square metre.
Our figures include everything you need to move in and start working: construction, furniture, electrical and plumbing. What isn’t included are the things that belong to your business: removalists, getting your computers and network working (your own IT provider usually does this) and connecting your own energy and internet.
What does that look like for a 300 square metre office?
On a 300 square metre office, those ranges work out to roughly $360,000 to $540,000 for a mid-range fitout and from $540,000 for a premium one. A refurbishment at $400 to $800 per square metre, if it covered the whole floor, would be roughly $120,000 to $240,000, though most refurbishments touch only some areas, so the real figure depends on scope.
| Per square metre | A 300 m² office | |
|---|---|---|
| Refurbishment | $400 to $800 | $120,000 to $240,000 if it covered the whole floor |
| Mid-range fitout | $1,200 to $1,800 | $360,000 to $540,000 |
| Premium fitout | From $1,800, often beyond $2,800 | From $540,000 |
None of this is a quote. It’s the same ranges multiplied out, so you can see the shape of a budget before anyone has visited your space. Most businesses also keep some contingency aside for changes and surprises in the building. How much is up to you.
What actually moves the number
The per square metre figure is a starting point. These are the things I look at first when I’m working out where a project will land.
The condition of the existing space. A bare shell costs more to fit out than a space with serviceable ceilings, flooring and services already in place. If the previous tenant left a kitchen, bathrooms or a comms room in good condition, there may be plenty you can reuse.
How many enclosed rooms you need. Open plan is cheaper than a layout with lots of meeting rooms, glass partitions and offices, because every room brings more than a wall. A new meeting room often needs sprinklers moved or added, and its own air conditioning control so it doesn’t end up too hot. Not every room needs the same level of privacy either. A boardroom used for confidential conversations might need walls that run right up to the concrete slab, while an everyday meeting room usually doesn’t.
The quality of finishes. The gap between mid-range and premium is mostly in the details: joinery, flooring, lighting and kitchen finishes such as stone benchtops. You see them every day, and they age very differently. More affordable finishes focus on being practical and hard-wearing.
Custom or off the shelf. Custom joinery and furniture cost more upfront, but they’re designed for your space. Off the shelf is faster and cheaper, though it may not use the floor as well.
The building’s age and services. Older buildings sometimes need mechanical, electrical or fire upgrades to meet current codes before the fitout can begin. Some of that isn’t visible until a ceiling is opened, which is why we get up into the ceiling to see what’s there before a layout is final. Almost every fitout also needs landlord approval and a building permit, and both add cost and time, particularly on more complex projects.
Your timeline. If you need it done fast, it costs more. A shorter program means more trades on site at once, often including weekend work. Planning the timeline early is one of the easiest ways to keep costs under control.
Try this: count the enclosed rooms in your current office and note which ones are booked every day. That tells you more about how many you need in the new space than a wish list does.
Where can you save without making the space worse?
If I had to pick one way to save that nobody notices, it would be reusing what already works. Ceilings, walls, flooring, kitchens and services that are in good shape can often stay, and the money goes into the parts people actually see and use. Cutting quality across the board tends to save less than it seems, and it shows quickly.
The other big saving comes from being deliberate about where you spend. Reception might get stone and custom joinery, because it’s the first thing clients see, while the storeroom gets standard finishes and nobody minds. It doesn’t have to be expensive, but it does need to be planned. Our post on fitout or refurbishment covers when a targeted update does the job for less than starting again.
Try this: before you talk to a fitout company, mark up a floor plan with three colours: where clients go, where your team spends the day, and the rooms only a few people use. It makes the first budget conversation much quicker.
What to plan for besides the build
A few things often catch businesses off guard.
Make-good on your current lease. Your lease may require you to return your current space to its original condition before you leave. That can be a significant cost (stripping out the fitout, patching walls and repainting), and it needs to sit in your budget from the start. We help clients understand exactly what their lease requires before they commit to anything. If make-good is on your list, our page on office make-good explains what it can involve and when to start planning for it.
Removalists, IT setup and utilities. Moving your team and equipment, getting your computers and network working (usually your own IT provider) and connecting your own energy and internet suppliers are your business’s to arrange, so they need their own line in your budget.
A contingency. On any fitout, it’s sensible to keep an allowance above your quoted figure for changes, unexpected building conditions or decisions that shift during the build. How much depends on your business and the building.
What should a quote actually tell you?
A good quote makes clear what’s included, what isn’t, and which items are allowances rather than fixed prices. Price differences between quotes usually come down to what’s included, so the detail matters.
Here’s an example I see a lot. One quote allows for two data cables to each of 100 workstations, and another allows for one. The second looks cheaper on paper, but if your office needs two, it ends up costing you more once the extra cabling is added. Our guide on how to read an office fitout quote walks through what to check before you compare totals. If you’re still choosing who to work with, our post on what to look for in an office fitout company covers what else to check.
Try this: ask every company you’re talking to for a written list of what isn’t included. If two quotes are far apart, that list usually explains why.
When should you start planning?
Earlier than most people expect. The build itself generally takes 8 to 14 weeks, and discovery, design and permits all come before that, which is why the planning window is longer than the build.
If you’re moving, I’d start the conversation around 12 months before your lease ends, so you have time to find the right space and get a builder to look at it before you sign. If you’re staying and refurbishing, allow at least 4 to 6 months. That gives you time to get the design right and work through approvals without making rushed decisions because the clock is running.
If you’re already working to a tight deadline, talk to us early anyway. We can often find ways to shorten the program where the project allows. Our guide on how to plan an office fitout sets out the steps in order, and if a lease end is driving your date, our month-by-month countdown shows what to decide and when.
So what will my fitout cost?
I can’t give you a real number until I’ve seen your space and understood what you’re trying to achieve. What I can do is have an early conversation, give you a realistic sense of what your budget will get you, and make sure there are no surprises further down the track.
That first conversation costs nothing. If it helps, send through a floor plan beforehand and we’ll come with some early thoughts.
Frequently asked questions
How much does a commercial fitout cost per square metre in Australia?
In Melbourne, most office fitouts cost between $1,200 and $2,800 or more per square metre in 2026, from mid-range to premium. Where yours lands depends on the condition of the space, how many enclosed rooms you need and the finishes you choose.
Do you handle the whole fitout, from design to construction?
Yes. Design, approvals and construction sit under one contract, and the same small team runs your project from the first site visit to the day you move in. You won't need to find a designer, a builder and a project manager and keep them talking to each other. That's our job.
Is furniture included in the cost of a fitout?
In our figures, yes. Furniture is included along with electrical and plumbing. Quotes don't always include the same things, so when you compare them, check what each one covers so you're comparing like with like.
How long does an office fitout take?
The build itself usually takes 8 to 14 weeks, depending on the size of the space. Discovery, design and permits come before that. If you're moving, start talking to a fitout company around 12 months before your lease ends. If you're staying and refurbishing, allow at least 4 to 6 months.