How long does an office fitout take?

The short answer. The build itself generally takes 8 to 14 weeks, depending on the size of the space. Discovery, design and approvals come before that, so allow at least 4 to 6 months from the first conversation to moving in, and around 12 months if you're also finding a new office. A targeted refurbishment generally takes 4 to 8 weeks.
It’s one of the first questions people ask, usually with a lease end date already in mind. The honest answer has two parts: how long the build takes, and how long everything before it takes. The build is the part you can see, but the earlier stages are what decide when it can start.
Here’s how a fitout runs with us, stage by stage, and what tends to move the dates.
How long does an office fitout take in Melbourne?
The build itself generally takes 8 to 14 weeks, depending on the size of the space. Before it, there’s discovery, design and approvals, and how long those take depends on the project. From the first conversation to moving in, allow at least 4 to 6 months, and around 12 months if you’re also finding a new office.
That’s why a fitout that “only takes 10 weeks” can still feel like it arrived in a rush. The build might be 10 weeks, but the decisions, the drawings, the permits and the orders all have to happen first.
Discovery: understanding what you need
Every project starts with a site visit and a real conversation about your budget, your timing and how your team works. If you haven’t signed a lease yet, this is when we can tell you what a space will really cost to fit out before you commit to it.
How long discovery takes depends mostly on you: how clear the brief is and how quickly the people who need to agree can get in a room together. It ends with a realistic picture of cost and timing, before any drawings are done.
Design development: drawings you can sign off
Next come concept plans, so you can see how the space will work and change your mind while it’s still cheap to. Then the detailed drawings, finishes and a proposal you can take to your board.
This is the stage where time is easiest to lose and easiest to save. Changes on paper cost very little, while changes on site cost time and money, so it’s worth asking every question here. Projects move fastest when one person in your business can make decisions without waiting for a committee.
Try this: before design starts, agree who in your business signs off the layout and finishes, and how quickly they can turn decisions around.
Site commencement: permits, approvals and ordering
Before anyone picks up a tool, the permits, your landlord’s approvals, the schedule and the trades are locked in. Most office fitouts need a building permit, and most leases need the landlord’s consent before work starts. Both take time, and they’re often the part people forget to count.
This is also when anything with a long lead time gets ordered, like glass walls, custom joinery, some furniture and imported light fittings. Ordering them now means they aren’t holding things up later. The stage ends with a start date and a schedule you can plan your move around.
Construction: usually 8 to 14 weeks
This is the build, and it generally takes 8 to 14 weeks depending on the size of the space. We build to the schedule we agreed, and you get a weekly walk-through so you always know where things are.
During a full fitout, your team will need to work somewhere else, or keep working in the old office if you’re moving. Our post on whether you can stay in your office during a fitout covers how to plan for both.
Handover: the last details
At handover, we walk through the finished space with you and sort out any last details we spot together, so everything works as agreed before your team moves in. It’s also when the move itself happens: IT and data, furniture and letting clients know where to find you.
If you’re leaving an old office, its make-good often runs alongside this stage. It’s the work your lease may require to return the space to its original condition, and it’s worth planning for from the start.
How long does a refurbishment take?
A targeted refurbishment generally takes 4 to 8 weeks, depending on the size of the space. It’s quicker because less changes: the layout and most of the services stay, and the work focuses on the areas that need it.
Design and approvals still come first, so allow time for those too. Depending on the work, a refurbishment can sometimes be staged so your team keeps using part of the office. Our post on fitout or refurbishment helps you work out which one you need.
What makes a fitout take longer?
A few things push dates out more than anything else:
Late decisions. When an answer takes two weeks to come back, everything behind it waits too. This is the most common cause of delay.
Changes once building has started. Moving a wall on paper is quick. Moving it on site means rework and new materials.
Long lead items. Custom joinery, glass, some furniture and imported fittings can take weeks to arrive, which is why we order them during site commencement.
The building. Older buildings can turn up surprises once a ceiling is opened, and some buildings limit when noisy work can happen or how the lifts can be used.
Approvals. Permits and landlord consent take as long as they take, so they need room in the plan.
When should you start?
Earlier than feels necessary. If you’re moving, start around 12 months before your lease ends, so there’s time to find the right space and have it looked at before you sign. If you’re staying and refurbishing, allow at least 4 to 6 months.
Our month-by-month countdown works back from your lease end date, and our post on how to plan an office fitout sets out the steps in order.
Try this: find your lease end date and count back 12 months. If that date has already passed, it’s worth a conversation sooner rather than later.
If you’d like to talk through your own timeline, feel free to reach out. You can see the whole process on our How a project runs page.
Frequently asked questions
How long does a Melbourne office fitout take?
The build itself generally takes 8 to 14 weeks, depending on the size of the space. Discovery, design and approvals come before that, so allow at least 4 to 6 months from the first conversation to moving in, and around 12 months if you're also finding a new office.
How long does an office refurbishment take?
A targeted refurbishment generally takes 4 to 8 weeks, depending on the size of the space. Design and approvals come before the work starts.
What makes a fitout take longer?
Late decisions, changes once building has started, long lead items like custom joinery and glass, surprises in older buildings, and permits and landlord approvals. Most of these can be planned for if they're picked up early.
When should I start planning before my lease ends?
Around 12 months before your lease ends if you're moving, and at least 4 to 6 months if you're staying and refurbishing.